Dunton site works are progressing well at Colindale Gardens. The project contracted by Redrow Homes involves the disposal of approximately 30,000m3 of inert material off-site, site levelling, localised filling in block areas, and on-site crushing operations – it’s currently on it’s 8th week of activity.
This week marked our 1000th load since starting works on the 19th of November! Here are some photos from the site.