Menu Close
Pushing out layers processing and rolling up layers at KV

Project Updates – September

The end of September draws near, but we have been lucky with the weather, meaning another productive month for Dunton.

At Hertford, Phase 1 is down to the top of the pile mat, ready for the next stage in the works, and more structures are being unearthed, keeping our plant operators very busy. The final cut has been completed and the troublesome foundation has finally been removed. As the areal shots proved, the team did a great job on the demolition of the wall of River Lea.

Them wagons a keep on rollin at Hertford Hertford North Site before and after River Lea wall demolition

At Kilnwood Vale, fantastic outputs have been achieved. At the area of what was the old Bewbush Brook, unsuitable material had been removed.

Cutting unsuitable material out of what was the old Bewbush Brook Processing and picking waste material down at KV

In September, the weather was ideal for Holly Lane to make good progress. As a result of the team’s determination, the final trim commenced. Ground remediation on an old landfill site could mean unusual discoveries, and it’s very true at Holly Lane.

Fridays at Holly Lane finding the best fill material on the site to date

At the Ascot Gasworks, the pile mat in the F Block is being placed, paving the way for further works to commence.

ascot Installing the piling mats WhatsApp Image at

Paragon Park is in phase 2 of the noise bund construction made out of recycled materials, and it now measures 8.5m.

paragon park bund phaseCurrently m paragon park bund phase