Dunton is proud of the creative ways we maximise the use of construction materials and minimise the impact on the environment.
A great example of our capability to help our Clients is the 300m long, 9m high bund is made from earth and recycled materials, supported by a geogrid retaining solution.
We stepped into phase two, constructing this bund for Persimmon Homes.
|
Moreover, we are progressing well on the first phase of the remediation of the former landfill site at Erdington.
Works involve excavation, processing and re-engineering of landfill materials to produce an engineered platform for redevelopment.
![]() |
![]() |
Other big news is that Dunton has been awarded another contract on HS2, this time for BBV on the Bromford tunnel diaphragm wall excavation. We broke ground this week.
![]() |
![]() |